CN – Milton Intermodal Rail and Truck Distribution Facility – Ontario - Project Profile

CN – Milton Intermodal Rail and Truck Distribution Facility – Ontario - Project Profile

  • January 2018 •
  • 7 pages •
  • Report ID: 4433249
Synopsis
"CN – Milton Intermodal Rail and Truck Distribution Facility – Ontario- Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "CN – Milton Intermodal Rail and Truck Distribution Facility – Ontario- Project Profile" is part of Timetric’s database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary
Canadian National Railway (CN) is planning to build a distribution facility in Milton, Ontario, Canada.

The project involves the construction of an intermodal rail and truck distribution facility on 161.8ha of land. It includes the construction of train sheds, administrative space, storage units, loading and unloading facilities and related facilities, the installation of signal systems, and the laying of railway lines.

In January 2016, CN submitted environmental Impact Statement (EIS) to the Canadian Environmental Assessment Agency to review the project.

On March 15, 2016, MTC asked CN to provide additional information for environmental assessment.

On June 8, 2016, Milton Town Council (MTC) invited the public for public hearing.

In December 2016, MTC formed three member panel to review the project.

On April 21, 2017, The review panel requested additional information on the project.

On May 5, 2017, The review panel requested for additional information again.

In May 2017, The review panel planned to visit site for better understanding of spatial orientation.

In October 2017, Environmental assessment on the project in progress.

CN awaiting for approvals.

Scope
The project involves the construction of an intermodal rail and truck distribution facility on 161.8ha of land in Milton, Canada.

The US$196 million project includes the following:
1. Construction of train sheds
2. Construction of an administrative space
3. Construction of storage units
4. Construction of loading and unloading facilities
5. Installation of signal systems
6. Laying of railway lines

Reasons To Buy
• Gain insight into the project.
• Monitor the latest project developments.
• Identify key project contacts.
Loading...

We are very sorry, but an error occurred.
Please contact support@reportbuyer.com if the problem remains.

Country=Canada Industry=Construction ParentIndustry=HeavyIndustry Date=201801 Publisher=Timetric Price=1000