TCC – Napanee Gas-Fired Combined Cycle Power Plant 900 MW – Ontario - Project Profile

TCC – Napanee Gas-Fired Combined Cycle Power Plant 900 MW – Ontario - Project Profile

  • March 2018 •
  • 7 pages •
  • Report ID: 4892165
Synopsis
"TCC – Napanee Gas-Fired Combined Cycle Power Plant 900 MW – Ontario - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "TCC – Napanee Gas-Fired Combined Cycle Power Plant 900 MW – Ontario - Project Profile" is part of Timetric’s database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary
TransCanada Corp (TCC) is undertaking the construction of Combined Cycle Generation Station project in Ontario, Canada.

The project involves the construction of a 900MW Combined Cycle Generation plant.A combined cycle plant uses both a gas turbine and a steam turbine to produce electricity.

Electricity is generated first in the gas turbine cycle using natural gas fuel and then the steam turbine cycle.

The project includes the construction of powerhouse, substations and related infrastructure and the installation of generators, steam turbines and gas turbines.

Kiewit Power has been appointed as engineering design contractor.

On December 17, 2012, TPP signed a 20-year power purchase agreement with Ontario Power Authority (OPA).

TCC has completed the environmental study stage of the proposed facility.

In October 2014, TCC has signed a host community agreement with the Town of Greater Napanee.

On February 4, 2015, Matrix North American Construction Ltd was appointed as construction contractor.

ES Fox Ltd is responsible for the Outside Boundary Limits (OBL) work (civil contractor).

Construction works on the project commenced in February 2015 and are scheduled to complete by the fourth quarter of 2018.

Scope
The project involves the construction of a 900MW gas-fired power plant in Southeastern Ontario, Canada.

The US$1,300 million project includes the following:
1. Construction of gas storage tanks
2. Construction of fuel processing units and cooling tower
3. Construction of powerhouse and substations
4. Installation of steam and gas turbine generator
5. Installation of transmission lines

Reasons To Buy
• Gain insight into the project.
• Monitor the latest project developments.
• Identify key project contacts.
Loading...

We are very sorry, but an error occurred.
Please contact support@reportbuyer.com if the problem remains.

Country=Canada Industry=Construction ParentIndustry=HeavyIndustry Date=201803 Topic=Demand Publisher=Timetric Price=1000