"SOGEM – Gouina Hydroelectric Power Plant 140 MW – Mali- Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "SOGEM – Gouina Hydroelectric Power Plant 140 MW – Mali- Project Profile" is part of Timetric’s database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary
Societe de Gestion de IEnergie de Manantali(SOGEM) is undertaking the development of hydroelectric power plant in Kayes, Mali.

The project involves the construction of 140MW hydroelectric power plant with a capacity of 620 GW-hour per year. It includes the construction of a powerhouse, a substation, a diversion tunnel, access roads and related infrastructure, the installation of three 49MW Kaplan turbines, generators and transformers, and the laying of transmission lines.

Coyne et Bellier conducted a feasibility study on the project.

On May 6, 2011, Agence Francaise de Developpement (AFD) and OMVS signed a grant agreement for the project.

In July 2011, SOGEM awarded a service contract to Oreade-Breche for the environmental and social study.

On January 4, 2013, the Malian government and The Export-ImportBank of China signed a US$345 million loan agreement to finance the project.

In September 2013, final reports of the Environmental and Social Impact Assessment (ESIA), the Environmental and Social Management Plan (ESMP) and the Resettlement Action Plan (RAP) were submitted to OMVS and AFD.

Sinohydro Group Ltd has been appointed as the main contractor and the contract value is US$326 million.

On December 17, 2013, groundbreaking ceremony was held and construction works commenced.

Construction works are underway.

Scope
The project involves the construction of a 140MW hydroelectric power plant with capacity of 620 GWh per year in Kayes, Mali.

The US$345 million project includes the following:
1. Construction of a powerhouse
2. Construction of a substation
3. Construction of a reservoir
4. Installation of three 49MW Kaplan turbines
5. Installation of generators
6. Installation of transformers
7. Laying of transmission lines
8. Construction of related facilities

Reasons To Buy
• Gain insight into the project.
• Monitor the latest project developments.
• Identify key project contacts.
Loading...

We are very sorry, but an error occurred.
Please contact support@reportbuyer.com if the problem remains.

Country=Mali Industry=Construction ParentIndustry=HeavyIndustry Date=201801 Topic=Trade Publisher=Timetric Price=1000