KCP – Phu Yen Industrial Zone Biomass Power Plant 60 MW – Phu Yen Province - Project Profile

KCP – Phu Yen Industrial Zone Biomass Power Plant 60 MW – Phu Yen Province - Project Profile

  • March 2018 •
  • 6 pages •
  • Report ID: 4474963
Synopsis
"KCP – Phu Yen Industrial Zone Biomass Power Plant 60 MW – Phu Yen Province - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "KCP – Phu Yen Industrial Zone Biomass Power Plant 60 MW – Phu Yen Province - Project Profile" is part of Timetric’s database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary
KCP Vietnam Industries Ltd (KCP) is undertaking the construction of a biomass power plant in Phu Yen Industrial Zone of Phu Yen Province, Vietnam.

The project involves the construction of a 60MW biomass power plant and will be executed in two phases.

The first phase includes the construction of a 30MW biomass power plant; the second phase includes the expansion of the capacity from 30MW to 60MW.

The project includes the construction of a cooling tower, a powerhouse, a substation, storage tanks, ash collector units and other related facilities, the installation of steam turbines and generators, and the laying of transmission lines.

Vietnam Applied Technical Co. Ltd (VATEC) has been appointed as the study consultant.

In September 2015, the Government of Vietnam approved the project plans.

Construction commenced on the first phase in the fourth quarter of 2015 and was completed in the first quarter of 2017.

Construction activities on the second phase are underway.

Scope
The project involves the construction of a 60MW biomass power plant in Phu Yen Province, Vietnam.

The US$57 million project includes the following:
1. Construction of a powerhouse
2. Construction of a substation
3. Construction of storage tanks
4. Construction of ash collector units
5. Installation of steam turbines
6. Installation of generators
7. Laying of transmission lines

Reasons To Buy
• Gain insight into the project.
• Monitor the latest project developments.
• Identify key project contacts.
Loading...

We are very sorry, but an error occurred.
Please contact support@reportbuyer.com if the problem remains.

Country=Vietnam Industry=Bioenergy ParentIndustry=HeavyIndustry Date=201803 Publisher=Timetric Price=1000