NTPC/BSPHCL – Nabinagar Coal-Based Thermal Power Plant 1980 MW – Bihar - Project Profile

NTPC/BSPHCL – Nabinagar Coal-Based Thermal Power Plant 1980 MW – Bihar - Project Profile

  • March 2018 •
  • 10 pages •
  • Report ID: 4857469
Synopsis
"NTPC/BSPHCL – Nabinagar Coal-Based Thermal Power Plant 1980 MW – Bihar - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "NTPC/BSPHCL – Nabinagar Coal-Based Thermal Power Plant 1980 MW – Bihar - Project Profile" is part of Timetric’s database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary
Nabinagar Power Generating Company Pvt. Ltd, a joint venture of National Thermal Power Corporation (NTPC) and Bihar State Power Holding Company Ltd (BSPHCL), is undertaking the Nabinagar Thermal Power Plant project at Nabinagar in Aurangabad District, Bihar, India.

The project involves the construction of 1,980MW coal based thermal power plant with three units of 660MW each. It also includes construction of a coal washing unit, water transmission pipeline, raw water storage tanks, switchyard for power evacuation, power house and installation of turbines, generators, and laying of transmission lines.

In January 2012, NTPC received approval from the state government for construction.

On January 28, 2012, the construction works commenced with the laying of foundation.

In March 2012, BGR Energy Systems Ltd was appointed to supply super-critical boilers. Radix was appointed to undertake site leveling works for the project.

In February 2013, Bharat Heavy Electricals Ltd (BHEL) bagged a prestigious contract of worth US$536 million for the supply of the Steam Generator Package for 3 coal-fired thermal units of 660MW each with supercritical parameters.

In February 2013, Alstom Bharat Forge Power Ltd (ABFPL), the joint venture company between Alstom and Bharat Forge, secured turbine islands supply contract of worth US$468 million.

ABFPL’s scope of work includes engineering, manufacturing, supply, erection and commissioning of three 660 MW supercritical units.

On March 21, 2013, Alstom was awarded a contract worth US$115 million by BHEL to supply components for three units of 660MW supercritical boilers.

Under the scope of the contract, Alstom will co-operate with BHEL in designing the boilers and supply identified pressure parts of the 660MW supercritical boilers, along with pulverisers and airpreheater components. It will also assist BHEL with technical advisors during the erection and commissioning of the units.

On March 29, 2013, Tata Robins Fraser (TRF) secured a US$66 million order from NPGCL. The order is for designing, engineering, manufacturing, supplying, erecting, testing and commissioning of the plant.

On October 21, 2013, ALSTOM T&D India Ltd was awarded a contract of worth US$19 million to supply power transformer.

Siemens Ltd has been appointed as supply contractor.

On August 20, 2016, BHEL invited tenders for erection and testing of electrical for the unit I of the project, with a submission due date on September 12, 2016.

Construction works on the first unit expected to be completed by the end of March 2018, second unit by July 2018 and the third unit by January 2019.

Scope
The project involves the construction of a 1,980MW coal based power plant at Nabinagar of Aurangabad District, Bihar.

The US$2,574 million project includes the following:
1. Construction of coal based thermal power plant unit I of 660 MW
2. Construction of coal based thermal power plant unit II of 660 MW
3. Construction of coal based thermal power plant unit II of 660 MW
4. Construction of a coal washing unit
5. Construction of water transmission pipeline
6. Construction of raw water storage tanks
7. Construction of switchyard for power evacuation
8. Construction of power house and
9. Installation of turbines
10. Installation of generators
11. Laying of transmission lines

Reasons To Buy
• Gain insight into the project.
• Monitor the latest project developments.
• Identify key project contacts.
Loading...

We are very sorry, but an error occurred.
Please contact support@reportbuyer.com if the problem remains.

Country=India Industry=ElectricPower ParentIndustry=HeavyIndustry Date=201803 Topic=Supply Publisher=Timetric Price=1000